Featured Post

PROFILE : My journey to Professional Registration - Innocent Gininda

Innocent Gininda shares his journey to becoming a registered Professional Engineer (PrEng), emphasizing the importance of mentorship, early preparation, and understanding ECSA requirements. He offers advice to aspiring PrEngs, highlighting the value of diverse feedback and a positive mindset. My journey to becoming a registered Professional Engineer (PrEng) culminated successfully in November 2024. I was fortunate to begin my career at a company with a Commitment and Undertaking (C&U) Agreement with ECSA and a robust mentorship program. This commitment to training engineers to the standard required for Professional Registration provided me with essential resources and a structured path to track my experience against ECSA requirements. Early exposure to these expectations instilled a positive outlook on registration and solidified my desire to achieve this milestone. My views on Professional Registration have remained consistently positive throughout this journey. Working alongside ...

CAREERTIPS: Check, Check & Check Again

Well experienced Construction Professional Steve Keightley - Smith shares a site incident that taught him a good lesson on being an effective Site Agent.                                                                      

In 1994 we had a good civil engineering job at the then Western Deep Levels 3 Shaft near Carletonville. Anglo American had checked the gold grade of the waste rock dump at No. 3 shaft and found that it averaged 3-4 grams /ton which was very high considering the dump was on the surface and all they needed to do was process the rock. They did not have sufficient milling capacity on the mine, so they decided to build a new milling plant. The job consisted of 2 large mill foundations, 2 x 10 m dia silos 30 m high, 2 x 50 m diameter thickeners, mill building, conveyors, transfer towers, control rooms, substations, various tank foundations, pipe rack foundations, roads, and paving.

It was my first job that involved sliding and we had a very experienced in-house sliding division. Two 30 m high 10 m diameter silos was easy work for a team that had built numerous grain silo complexes that were usually +- 10 silos +-40 m high with concrete coned roofs, and had also worked on the Sasol 2 & 3 chimneys +- 200 m high. The silos also had railway line rails, lining on the interiors of the silos to prevent the rock from the conveyors wearing away the insides of the concrete silos. We were working for Anglo American who had a huge amount of experience on building mine infrastructure from all the work they had done on the Free State gold mines. Western Deep Levels was also one of Anglos top gold mines and no expenses was spared to ensure this was a word class job. Anglo had learnt from experience to build their plants to a high standard to ensure they lasted.

The silos had 300 mm wide walls and recessed pockets at the top to support steel beams that held up the roof and supported the conveyors that fed the silos. The recessed pockets had 25 mm steel plates with fish tail lugs cast into the bottom of the pockets to weld the steel beams to.

We had a Liebherr 45/45 luffing jib tower crane on rails so we could move it between the 2 silos. Concrete was mixed by a 400 R diesel mixer with timber bulkheads to separate the aggregates and a cement store that stored the bags of cement. Concrete was volume batched with a team of laborer’s using wheelbarrows feeding the mixer with aggregate and cement. (Which was normal in those days)

The sliding team and concrete team worked 12 hours a day per shift 24 hours a day until the slide was finished.

Both slides went well. The shutter was stripped plus the access tower which had access stairs.

We continued with the construction of the rest of the plant. M&R Mechanicals were appointed as the structural & mechanical contractor. They arrived on site, did their establishment, and started getting deliveries of steel. One of the first activities was to pre-assemble the steel platform that sat on top of the silos. They had a 100-ton American lattice boom crane on wheels that they used to assemble the platform and then the big day arrived for them to lift it on top of the silo. This was their first big lift and the whole project & site team was there to watch their first big moment.

All went well with the lift but when they tried to lower the platform into the recessed pockets at the top of the silo the steel did not go deep enough into the silo and the beams stuck out the top of the silo. There was great consternation, drawings were quickly pulled out, measurements were taken, people were sent up in a bosuns chair to check and check again.  

We then got the bad news, the recesses in the top of the silo with the 25 mm steel plate with +-400 mm long fish tail lugs were cast too high up on the silo. They sent me up in the bosuns chair to check myself and I confirmed that the plates were cast in at the wrong level and the recesses were not deep enough.

The silos had sat for +- 3 months before the mechanical had arrived on site, and once the slide had been stripped and the access tower stripped, and the tower cranes stripped there was no way to get to the top of the silos, and no one had thought to double check them. We were too busy focusing on other areas of the plant and trying to keep to the program.

Now the challenges started. We had to find a team, as this was extra work, not in the allowable, build up access towers to each of the 4 big pockets and 2 smaller pockets on each silo, make work platforms 30 m up in the sky, break out the concrete, remove the steel plates with the fish tail lugs, set the right levels and grout in the steel plates & lugs with non- shrink grout.

The concrete had been standing for 3 months, so it was rock hard, it was a difficult job with heavy compressed air breakers and there was limited space for more than 2 people on the platform. I had to go up and check the progress and to check each pocket before they were cast, and it was not fun climbing up the scaffold to each pocket. There were no access stairs, so we climbed up the scaffold to the rest platforms every +- 6 m.

The M&R Lattice boom crane operator was real shit, and it cost us a case of beer every time he helped us to lift a jackhammer or to lift the heavy steel plates or grout. It cost us plenty of cases of beer.

We were under big pressure with Anglo as M&R were charging standing time for their silo team and the crane even though they were using them on other jobs.

I got so tired of climbing up each individual scaffold tower that I would climb up one, and then for the first time straddle the top of the silo and inch my way across to the next pocket. This was very slow and as I got used to being up there, I would just walk along the 300 mm wide wall 30 m up in the sky. Safet was not such a big issue in those days.

We eventually finished the work, double checked it, and told the project team that we were finished. They sent their people up in the bosuns chair and confirmed it was correct and M&R Mechanicals could carry on with their work. We stripped our scaffold towers and carried on with the rest of the work.

It cost us quite a lot of money for the standing time costs M&R Mechanicals had incurred and the clients QS`s were very quick to deduct the money in out next payment certificate. We were unable to claim it back from our sliding division as they were an inhouse division and we had only picked up the problem 3 months after they had finished work.

So, the moral of the story is – Check, Check and Check Again. As the site agent for the job, you are responsible for the job, the whole job. Don’t leave it up to others to check unless you trust them. You are the responsible person on the site and accountable for the site, and until the maintenance period is over, you have completed any remedial works, and received your final retention it’s your baby.


Steve Keightley - Smith is a Construction Professional with over 40 years of Civil Engineering, Building and associated Construction experience on Major Mining, Water Treatment, Railway, Industrial and Building Projects in Southern Africa. 

Steve has held senior management positions at Concor, Trencon and Basil Read. Was involved in a number of Joint Venture contracts with other major civils contractors. He also has experience in cross border construction activities in Zimbabwe, DRC, Mozambique, and Botswana and investigations in Namibia, Angola, Zambia and Uganda. 

He has also spent time on Grootegeluk coal mine, Medupi and Kusile power stations and the coal mines supplying the power stations. 

 

 

 

 

 

 

 

 

 

 

Comments