WHAT WERE THE CHALLENGES YOU FACED IN PHASE 1?
Phase 1 was essentially one of the first large civil contracts after Zimbabwe opened up. Zimbabwe supply infrastructure was in a bad state, with very few and limited local materials available and the majority of business were closed.
All major, cement, formwork, reinforcing and minor materials were imported, supplementary food supplies were imported weekly. All plant and vehicles, busses, offices accommodation units were imported. Diesel was supplied by the mine. Major earthworks were subcontracted out to a local contractor assisted by the mine on a plant buy back system and agreed rates.
The contract went through the `Billionaire stage` when the Zimbabwean dollar devalued and inflation dramatically increased. Everyone became billionaires on paper but starved, as the money had no value. Local banks rationed cash draws and the Government unilaterally took spare funds from your account with no recourse and payback. Black market was rife. This presented extreme challenges in the paying of the local labour teams, timeously. Petty cash draws ended up in carry bags full of local cash. At that stage, the local labour was largely untrained and still to be introduced to having their own accounts for bi – weekly and monthly wages payments.
Zimbabwean labour law insists on a morning teatime break with a pre-packed sugared tea brew issue. A cooked daily lunch regime was introduced. This was cooked on open fires at team cook areas, staples being Sadsa, Kapenta and vegetable relish, alternated with beef or chicken vegetable relish , butcher shops being unavailable, local beef was sourced live , price negotiated and meat prepared. Vegetables and staples were sourced from local markets when available, timber for cooking came from the bush clearing for the job.
|
Kitchen & Eating Area at Main Offices. |
The Contract allowed a 50% expat content.
This was needed as the local labour and foremen expertise was heavily lacking.
As expat R&R, transport and another add-ons are expensive these expat teams
were reduced during the contract as local teams became more HSE aware and more
experienced as well as experienced Zimbabwean foremen returned to Zimbabwe had become
available
We had challenges with a local reinforcing steel fixers due to nonpayment of labour and strikes re-nonpayment.
Bussing. We had our own busses arranged
transport routes with pickup points
Accommodation. Labour skilled accommodation. The compound allowed expats and
skilled labour accommodation. Distinction was salaried staff as opposed to hourly paid staff. Hourly paid staff stayed in their own homes and were bussed
from designated pickup points. Some labour walking 5 km home from the drop off points.
The compound was erected in FSM temporary units, ditto the site offices
The Senior accommodation stayed in
the nearest game park lodge at least 40 km away. Teams travelled to site and
back daily. to be onsite at 06h45 and leave site at 17hoo. During the contract, a mud-brick senior compound was constructed with a canteen and cooks.
This accommodation was sold to the
client at contract end, both FSM compound and Senior compound.
|
Phase 1 Senior Compound Still in use by Mine. |
WHAT WERE THE CHALLENGES YOU FACED IN PHASE 2?
Local Resources. We could
get cement from PPC in Bulawayo as they had a factory in Bulawayo 450 km away,
a truck turnaround time of 2 days up and 2 days return, with driver R&R a
week trip per truck. This became a
detailed logistical exercise. We had 4 silo’s 2 x 100t and 2 x 30t supplied by
PPC and also a large stockpile of bags We found that 2.5 full cement trucks
volume of cement had been stolen on the road up. The seal tags were in place,
but they had been taking the cement out the top tanker access lids. PPC had to
take this loss. The batch plant was a Namib with extra aggregate load bins to
expedite production. The best turnaround achieved was 18m3 /hr on a 30m3/hr
batch plant. This after increasing Conveyor tube diameters, Cement and water
hopper capacity and extra booster water pumps to force feed the water. We were
running 6 trucks with one in overhaul service rotation. Some pours ran greater
than 24 hours continuous. The Slides ran for 7 days continuous. Due to high
temperatures and distances from batch plant to site, the concrete was retarded.
|
Namid Karoo Batch Plant with Silos. |
The reinforcing steel in Harare was
limited and the quality was inconsistent, and the decision was taken to source
that from South Africa. This also caused delays as they would send
reinforcement in the wrong sequence and all the easy, not critical
reinforcement was sent early and the critical reinforcement (big bars) were
late. There were bar sizes that were too big to fit on the trucks without
permits resulting in some trucks being stopped on the road by the traffic
authorities. From previous experience in Phase 1 we imported stock rebar and
established a cutting and bending yard on site where we could cut and bend bar
shortages and drawing revision changes onsite.
We also established a precast yard near the main offices where the two different sizes of conveyor trestle foundations were precast, the Reinforced Earth panels and the late extra New Jersey barriers were cast and then transported to site via crane truck and installed.
We managed to find a small local
earthworks contractor but they had limited resources and especially at the
start of the job, they were under pressure to perform, as the job was spread out
over a wide area +-12 km and we needed to get going with a number of
different structures in different areas.
The silos were slid by Sanyati Construction from South Africa . The sliding team was competent. They delayed the
silo construction due to a late arrival on site with teams and equipment and delayed the removal of equipment
and containers after the job was complete.
Crushed aggregates became a
bottleneck with the local crusher failing continuously. We ended up importing a surge
stockpile from Harare, to cater for the crusher downtimes at huge cost. The jaw crusher and
the belts and conveyor pullers were old and needed repair but spare parts and cash-flow was a major challenge for a small crusher operator with a limited market.
Skilled Labour. In terms of
the contract we needed to use only Zimbabwean labour. Luckily we had worked
there previously and had a good local HR officer that could recruit all the
experienced skills we needed plus I had foremen that had worked for me before
that brought their own teams. That is a tremendous advantage where you have
skilled foremen and team leaders with their own local labour. We found that
many of the people that had worked on Phase one came back. This obviated
training raw labour and a far quicker start.
|
Senior Concrete Foreman Simba Mbende and Site Engineer Lawrence Mberikwazvo on top of the 14,000 ton Stockpile Tunnel. |
Skilled Staff Again we managed to get a lot of the local staff that we had worked with previously. The
contract heavily restricted the number of expats allowed. I had a few expats in
key team leading and foremen positions. The number of expats were reduced to
about 5% of the total team.
We had an immense logistical
problem in the motivation of bringing in expats with at least 12 columns of
information per person required to be submitted to immigration and the Department of Labour.
Unfortunately, there was a definite aspect of ‘graft’ required in order to get
applications processed.
Logistics. Getting plant
and equipment through the border was a nightmare. The HO logistics department
really let us down by sending loads to the border with incomplete paperwork.
Some of our equipment sat at the border for +- 4 weeks.
Key pieces of equipment like the batch plant
and the 4 tower cranes were late getting onto site resulting in unnecessary and pressure at the start of the job. The tower cranes were
at the border for so long that all the copper wiring was stolen and when we
eventually got them to site, we needed a specialist crane mechanic to come to
site and rewire them resulting in more delays.
Poker vibrators that were bought
by the buying department in Johannesburg were of such poor quality that they broke down. There were
none available in Zimbabwe and at one stage we had +- 30 broken on site and a 2-week
lead time to get more on site. This delayed us a further +- 2 weeks with the few remaining pokers being transported from pour to pour to enable work to continue..
PPE provided was also of poor quality,
with boots lasting +-3 weeks before soles broke and delaminated.
We arranged that the Basil Read
labour was in green overalls as most other companies were in blue and other
colours. As the site is essentially 20 km in extent, it was easy to pick out
labour not working or travelling to the local shops, +-10 km away. These shops,
bank and supermarket had been erected in the period between Phase 1 and 2 at an
area called Ngezi Village.
Bussing.The contract required that the
local labour be drawn from the local communities within a 30 km radius of the
site. No poaching of mine labour was allowed. Rates were to be on par with mine labour
rates per category. Civils categories and mine labour categories do not overlap
much resulting in some un-happiness.
We therefore had 3 routes for labour pickup at
designated pickup points and after work offloading points. We had brought in our own
busses, one of these was locked up at the Department of Transport due to some obscure law
requiring tax payment of kms. travelled on public roads. All our routes were
along mine roads. We ended up paying a reduced fine, whilst struggling for 3
weeks to get the bus out of the vehicle pound.
|
Skilled Labour Flat-Pack Camp.
|
Staff Accommodation & Labour Accommodation. We knew that there was very limited accommodation on the mine, so we had ordered flat-pack container accommodation from China. This was a major challenge as the supplier was late in dispatching it from China and then instead of offloading it in Beira it was off loaded in Port Elisabeth. The Chinese fittings, plumbing are very inferior, The toilets having a 50mm discharge outlet and kept on jamming so ended up changing to SA toilets and cisterns with a 100mm dia outlet. We were unable to get replacement fittings from china. The subcontractor had a supply and erect contract. Site had to provide the electrical, water and plumbing reticulation, Septic tanks, DB Board, Water tanks and trestles and demand pressure water pumps. As the Mine water boreholes where often out of use the water supply was a challenge when there are 200 people in camp.
The senior staff started off staying at the same game farm 60 km from site, Pamazinda and Chengeta lodges until the flat-pack accommodation was erected. The mine did not allow us to stay in the previous Stef-Stocks compound. A local Zimbabwe timber house supplier (Wendy) house had moved off site 9 they had a small building and earthworks contract) and some of these units became available during the contract allowing overflow skilled labour, to be accommodated.
We also managed to arrange to take over and purchase an existing senior compound in prefab units, the mine allocated a piece of bush for a senior’s camp. This we fenced cut and trimmed and erected a mud-brick thatched dining, lounge, kitchen, and circular braai area with seating. Senior flat-pack units were erected in this bush camp.
Comments
Post a Comment